Zambia CDF Tracker

Bwana Mkubwa constituency

1 CDF projects tracked in Bwana Mkubwa, Copperbelt: budgets, status, contractors and sources.

Copperbelt Province · 1 published CDF projects tracked across all published years · per-project amounts not published in published budgets (0 of 1 projects publish amounts).

Approved: 1

Record: based on tender notices.

The audited record

The Auditor-General counted this constituency's projects in its audit of the CDF. These are the audit's own totals — a separate record from the council's published list above. The audit does not publish the projects name by name, so its totals are never added to the council list (some projects appear in both records). Figures are as printed in the Auditor-General's reports — where a report does not publish a figure, this page says so rather than estimating it.

Financial year 2024

ComponentTotal funds availableSpentUnspentUnspent / spent
Community ProjectsK19,613,051K17,796,869K1,816,1829% unspent · 91% spent
Empowerment GrantK4,174,733K3,736,118K438,61511% unspent · 89% spent
Secondary Boarding and Skills Development - BursariesK5,394,140K6,106,090-K711,950-13% unspent · 113% spent
LoansK7,180,873K6,515,248K665,6259% unspent · 91% spent
Administrative CostK1,703,026K2,699,229-K996,203-58% unspent · 158% spent

Community Projects: balance brought forward K19,613,051 · 2024 funding K0 · other receipts K0

Empowerment Grant: balance brought forward K2,174,733 · 2024 funding K2,000,000 · other receipts K0

Secondary Boarding and Skills Development - Bursaries: balance brought forward K3,177,717 · 2024 funding K2,216,423 · funds borrowed K0

Loans: balance brought forward K3,377,140 · 2024 funding K3,283,577 · other receipts K0 · loan repayments received K501,766 · interest accrued K18,390

Administrative Cost: balance brought forward K1,027,055 · 2024 funding K675,971 · other receipts K0

2023 cohort — brought forward: 5 projects

Implemented — 0 (0%)In progress — 3 (60%)Not implemented — 2 (40%)

2024 cohort — approved: 14 projects

Implemented — 3 (21%)In progress — 4 (29%)Not implemented — 7 (50%)

Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2024 — Appendices 2.1–2.5 (money) and Appendix 3 (project status). Read the report (PDF)

Financial year 2023

ComponentAmount receivedSpentUnspentUnspent / spent
Community ProjectsK15,198,297K6,896,431K8,301,86655% unspent · 45% spent
Empowerment GrantsK2,151,857K0K2,151,857100% unspent · 0% spent
Soft LoansNot published by constituency in the FY2023 report — its Appendix 2.3 repeats the Empowerment Grants table instead of a loans table.
Secondary Boarding and Skills Development - BursariesK5,397,641K2,429,320K2,968,32155% unspent · 45% spent
Administrative CostsK1,415,695K1,144,658K271,03719% unspent · 81% spent

2022 cohort — brought forward: 9 projects

Implemented — 7 (78%)In progress — 2 (22%)Not implemented — 0 (0%)

2023 cohort — approved: 13 projects

Implemented — 1 (8%)In progress — 0 (0%)Not implemented — 12 (92%)

Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2023 — Appendices 2.1–2.5 (money) and Appendices 3–4 (project status). Read the report (PDF)

?How to read
this tracker