Zambia CDF Tracker

Bweengwa constituency

26 CDF projects tracked in Bweengwa, Southern: budgets, status, contractors and sources.

Southern Province · 26 published CDF projects tracked across all published years · per-project amounts not published in published budgets (0 of 26 projects publish amounts). Funding year is published for 25 of 26.

Approved: 26

Record: based on approval lists.

2025 CDF — 25 projects

1x2 Science Laboratory at Nalutanda

Bweengwa · education

Not published · Approved

Chief Choongo Palace

Choongo East · administration

Not published · Approved

Completion of 1x2 Science Laboratory at Moonzwe Primary School

Kaila · education

Not published · Approved

Completion of 1x2 Staff House at Hamangaba Primary School

Hamangaba · education

Not published · Approved

Completion of Banakaila Maternity Annex

Kaila · health

Not published · Approved

Completion of Choongo Rural Health Centre

Choongo East · health

Not published · Approved

Completion of Moonzwe Maternity Annex

Kaila · health

Not published · Approved

Completion of Water Reticulation System at Monze Boarding School

Choongo East · water

Not published · Approved

Completion of the Rehabilitation of Chuungu Primary School

Choongo East · education

Not published · Approved

Construction of 2 Staff Houses at Nakasangwe and Ntandabale

Malundu · infrastructure

Not published · Approved

Construction of Choongo Rural Health Centre Supporting Structures (staff house, ablution block and water reticulation system)

Choongo East · health

Not published · Approved

Construction of Gonhwe Clinic (with Water Reticulation System)

Choongo West · health

Not published · Approved

Construction of Keemba Police Post

Keemba · security

Not published · Approved

Construction of Munthazhi Rural Health Centre (Clinic)

Bweengwa · health

Not published · Approved

Construction of Support Structures at Nachibuli Clinic (3-bedroomed staff house, ablution block and water reticulation system)

Keemba · health

Not published · Approved

Construction of a 2-Bedroomed Staff House at Mahiba

Hamusonde · infrastructure

Not published · Approved

Desks

All · education

Not published · Approved

Dipping Tank at Bweengwa Ward

Bweengwa · infrastructure

Not published · Approved

Dipping Tank at Kaila Ward

Kaila · infrastructure

Not published · Approved

Dipping Tanks in Choongo Ward

Choongo East · infrastructure

Not published · Approved

Dipping Tanks in Hamusonde Ward

Hamusonde · infrastructure

Not published · Approved

Drilling of a Borehole at Kabomba Village, Ntaamba

Hamusonde · water

Not published · Approved

Procurement of Dipping Chemicals

All · equipment

Not published · Approved

Road Maintenance

All · roads

Not published · Approved

Water Reticulation System with Animal Drinking Troughs at Hikaunu

Choongo West · water

Not published · Approved

Funding year not published — 1 projects

The audited record

The Auditor-General counted this constituency's projects in its audit of the CDF. These are the audit's own totals — a separate record from the council's published list above. The audit does not publish the projects name by name, so its totals are never added to the council list (some projects appear in both records). Figures are as printed in the Auditor-General's reports — where a report does not publish a figure, this page says so rather than estimating it.

Financial year 2024

ComponentTotal funds availableSpentUnspentUnspent / spent
Community ProjectsK13,737,476K13,827,097-K89,621-1% unspent · 101% spent
Empowerment GrantK1,170,000K1,080,000K90,0008% unspent · 92% spent
Secondary Boarding and Skills Development - BursariesK4,812,243K4,812,243K00% unspent · 100% spent
LoansK3,087,117K2,765,644K321,47310% unspent · 90% spent
Administrative CostK1,570,230K1,570,230K00% unspent · 100% spent

Community Projects: balance brought forward K15,021,310 · 2024 funding -K1,283,834

Empowerment Grant: balance brought forward K0 · 2024 funding K1,170,000

Secondary Boarding and Skills Development - Bursaries: balance brought forward K0 · 2024 funding K4,812,243

Loans: balance brought forward K1,063,032 · 2024 funding K1,731,361 · loan repayments received K260,850 · interest accrued K31,874

Administrative Cost: balance brought forward K0 · 2024 funding K1,570,230

2023 cohort — brought forward: 38 projects

Implemented — 38 (100%)In progress — 0 (0%)Not implemented — 0 (0%)

2024 cohort — approved: 62 projects

Implemented — 58 (94%)In progress — 1 (2%)Not implemented — 3 (5%)

Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2024 — Appendices 2.1–2.5 (money) and Appendix 3 (project status). Read the report (PDF)

Financial year 2023

ComponentAmount receivedSpentUnspentUnspent / spent
Community ProjectsK15,324,450K12,863,687K2,460,76316% unspent · 84% spent
Empowerment GrantsK2,150,800K2,526,898-K376,098-17% unspent · 117% spent
Soft LoansNot published by constituency in the FY2023 report — its Appendix 2.3 repeats the Empowerment Grants table instead of a loans table.
Secondary Boarding and Skills Development - Bursaries†Not publishedNot publishedNot publishedNot published
Administrative CostsK1,415,000K1,621,480-K206,480-15% unspent · 115% spent

† The report prints this constituency inside a district-combined figure; the split by constituency is not published.

2022 cohort — brought forward: 13 projects

Implemented — 12 (92%)In progress — 1 (8%)Not implemented — 0 (0%)

2023 cohort — approved: 41 projects

Implemented — 3 (7%)In progress — 19 (46%)Not implemented — 19 (46%)

Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2023 — Appendices 2.1–2.5 (money) and Appendices 3–4 (project status). Read the report (PDF)