Zambia CDF Tracker

Chama South constituency

1 CDF projects tracked in Chama South, Eastern: budgets, status, contractors and sources.

Eastern Province · 1 published CDF projects tracked across all published years · per-project amounts not published in published budgets (0 of 1 projects publish amounts).

Completed: 1

Record: based on council newsletters. No approval list has been published for this constituency — the public record here starts at handover.

The audited record

The Auditor-General counted this constituency's projects in its audit of the CDF. These are the audit's own totals — a separate record from the council's published list above. The audit does not publish the projects name by name, so its totals are never added to the council list (some projects appear in both records). Figures are as printed in the Auditor-General's reports — where a report does not publish a figure, this page says so rather than estimating it.

Financial year 2024

ComponentTotal funds availableSpentUnspentUnspent / spent
Community ProjectsK35,646,625K31,074,287K4,572,33813% unspent · 87% spent
Empowerment GrantK1,582,941K2,407,500-K824,559-52% unspent · 152% spent
Secondary Boarding and Skills Development - BursariesK4,755,202K2,442,588K2,312,61449% unspent · 51% spent
LoansK3,935,482K3,370,000K565,48214% unspent · 86% spent
Administrative CostK1,266,617K2,734,870-K1,468,253-116% unspent · 216% spent

Community Projects: balance brought forward K24,448,181 · 2024 funding K11,198,444

Empowerment Grant: balance brought forward K47,257 · 2024 funding K1,535,684

Secondary Boarding and Skills Development - Bursaries: balance brought forward K915,991 · 2024 funding K3,839,211

Loans: balance brought forward K260,299 · 2024 funding K2,622,717 · loan repayments received K574,744 · interest accrued K477,722

Administrative Cost: balance brought forward K256,298 · 2024 funding K1,010,319

2023 cohort — brought forward: 1 projects

Implemented — 0 (0%)In progress — 0 (0%)Not implemented — 1 (100%)

2024 cohort — approved: 20 projects

Implemented — 13 (65%)In progress — 7 (35%)Not implemented — 0 (0%)

Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2024 — Appendices 2.1–2.5 (money) and Appendix 3 (project status). Read the report (PDF)

Financial year 2023

ComponentAmount receivedSpentUnspentUnspent / spent
Community ProjectsK14,762,086K9,978,022K4,784,06432% unspent · 68% spent
Empowerment GrantsK2,071,872K2,104,600-K32,728-2% unspent · 102% spent
Soft LoansNot published by constituency in the FY2023 report — its Appendix 2.3 repeats the Empowerment Grants table instead of a loans table.
Secondary Boarding and Skills Development - BursariesK5,179,679K681,650K4,498,02987% unspent · 13% spent
Administrative CostsK1,363,074K2,306,575-K943,501-69% unspent · 169% spent

2022 cohort — brought forward: 23 projects

Implemented — 5 (22%)In progress — 18 (78%)Not implemented — 0 (0%)

2023 cohort — approved: 9 projects

Implemented — 3 (33%)In progress — 2 (22%)Not implemented — 4 (44%)

Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2023 — Appendices 2.1–2.5 (money) and Appendices 3–4 (project status). Read the report (PDF)

?How to read
this tracker