Zambia CDF Tracker

Chembe constituency

13 CDF projects tracked in Chembe, Luapula: budgets, status, contractors and sources.

Luapula Province · 13 published CDF projects tracked across all published years · per-project amounts not published in published budgets (0 of 13 projects publish amounts).

Completed: 13

Record: based on commissioning / handover reports. No approval list has been published for this constituency — the public record here starts at handover.

The audited record

The Auditor-General counted this constituency's projects in its audit of the CDF. These are the audit's own totals — a separate record from the council's published list above. The audit does not publish the projects name by name, so its totals are never added to the council list (some projects appear in both records). Figures are as printed in the Auditor-General's reports — where a report does not publish a figure, this page says so rather than estimating it.

Financial year 2024

ComponentTotal funds availableSpentUnspentUnspent / spent
Community ProjectsK27,219,825K16,073,121K11,146,70441% unspent · 59% spent
Empowerment GrantK3,745,531K1,944,959K1,800,57248% unspent · 52% spent
Secondary Boarding and Skills Development - BursariesK6,681,297K2,982,282K3,699,01555% unspent · 45% spent
LoansK4,905,058K3,431,323K1,473,73530% unspent · 70% spent
Administrative CostK1,623,284K14,726,203-K13,102,919-807% unspent · 907% spent

Community Projects: balance brought forward K15,764,264 · 2024 funding K11,455,561

Empowerment Grant: balance brought forward K61,505 · 2024 funding K3,684,026

Secondary Boarding and Skills Development - Bursaries: balance brought forward K2,862,777 · 2024 funding K3,818,520

Loans: balance brought forward K4,263,280 · 2024 funding K0 · loan repayments received K194,212 · interest accrued K447,566

Administrative Cost: balance brought forward K618,410 · 2024 funding K1,004,874

2023 cohort — brought forward: 2 projects

Implemented — 2 (100%)In progress — 0 (0%)Not implemented — 0 (0%)

2024 cohort — approved: 20 projects

Implemented — 8 (40%)In progress — 11 (55%)Not implemented — 1 (5%)

Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2024 — Appendices 2.1–2.5 (money) and Appendix 3 (project status). Read the report (PDF)

Financial year 2023

ComponentAmount receivedSpentUnspentUnspent / spent
Community ProjectsK14,279,546K11,327,217K2,952,32921% unspent · 79% spent
Empowerment GrantsK2,151,857K2,139,534K12,3231% unspent · 99% spent
Soft LoansNot published by constituency in the FY2023 report — its Appendix 2.3 repeats the Empowerment Grants table instead of a loans table.
Secondary Boarding and Skills Development - BursariesK5,379,641K2,230,502K3,149,13959% unspent · 41% spent
Administrative CostsK1,415,695K1,155,209K260,48618% unspent · 82% spent

2022 cohort — brought forward: 18 projects

Implemented — 16 (89%)In progress — 2 (11%)Not implemented — 0 (0%)

2023 cohort — approved: 6 projects

Implemented — 1 (17%)In progress — 2 (33%)Not implemented — 3 (50%)

Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2023 — Appendices 2.1–2.5 (money) and Appendices 3–4 (project status). Read the report (PDF)

?How to read
this tracker