Lusaka Province · 45 published CDF projects tracked across all published years · K16.1m in published budgets (38 of 45 projects publish amounts). Funding year is published for 33 of 45.
Approved: 12 · Completed: 9 · Funded: 10 · In progress: 13 · Status not stated: 1
Record: based on CDFC minutes, published project lists.
2025 CDF — 7 projects
Construction of 1x2 laboratory at Kapoche Secondary School
Kapoche · education
Not published · Funded
Construction of ablution block at Zalapango Primary School
sanitation
Not published · Funded
Construction of male dormitory at Mwavi Secondary School
education
Not published · Funded
Construction of maternity wing in Mburuma Chiefdom
health
Not published · Funded
Construction of semi-detached staff house in Mkaliva Ward
Mkaliva Ward · education
Not published · Funded
Construction of single staff house at Mukando
education
Not published · Funded
Procurement of low-bed trailer
equipment
Not published · Funded
2022 CDF — 26 projects
Completion of maternity wing at Boma Clinic (roofing, flooring, electricals, plumbing)
Dzalo · health
K150,000 · Funded
Connection of water pipes to Lusaka Water supply (1.5 km) at Soweto Area
Kavula · water
K320,000 · Completed
Construction of 1x2 classroom block for Early Childhood Education at Mangelengele Area
Mburuma · education
K514,415 · In progress
Construction of 1x3 classroom block at Kaunga Primary School (Kaunga B)
Kaunga · education
K624,461 · In progress
Construction of Early Childhood Pre-School (1x2 classroom block) at Mukando Village
Kaunga · education
K398,000 · In progress
Construction of foot bridge across Rufunsa Stream at Janeiro
Kabowo · infrastructure
K412,300 · Completed
Construction of girls and boys dormitory at Kakaro Secondary School
Phwazi · education
K720,000 · In progress
Construction of health post at Chiriwe (Undi)
Chiriwe · health
K419,001 · In progress
Construction of market shelter at Lunya Market
Lunya · markets
K310,111 · Completed
Construction of maternity wing at Kaunga Health Post
Kaunga · health
K419,001 · In progress
Construction of semi-detached staff house at Kapoche Primary School
Kapoche · education
K894,944 · In progress
Construction of semi-detached staff house at Mankhokwe Primary School
Mankhokwe · education
K894,944 · In progress
Construction of semi-detached staff house at Mphuka Skills Training Centre
Mphuka · education
K894,944 · In progress
Construction of single staff house at Kasinsa Health Post
Mwalilia · health
K440,462 · In progress
Construction of single staff house at Mandombe Primary School
Mandombe · education
K440,562 · In progress
Equipping of borehole with reticulation system at Kavalamanja Village
M'kaliva · water
K215,000 · Completed
Equipping of reticulation system on borehole at Katondwe Primary School
Katondwe · water
K205,000 · Funded
Extension of water network to Kapyanika, Kamoba A and Kamoba B villages
Mandombe · water
K450,000 · In progress
Installation of rumbles on D145 at Nyaukwindi and patching of potholes along D145
Kapoche · roads
K93,000 · Completed
Procurement of road construction equipment - grader
All wards · equipment
K2,100,000 · Completed
Procurement of utility vehicle for monitoring of projects
All wards · administration
K1,500,000 · Status not stated
Purchase of engine boat at Kanyenze Village
Kavula · equipment
K50,000 · Completed
Rehabilitation of Chief's Arena (stands, shelters and stage) at Mburuma Arena
Mburuma · administration
K50,000 · Completed
Rehabilitation of Chief's Arena at Mphuka Arena
Mphuka · administration
K50,000 · Completed
Rehabilitation of commercial borehole and construction of water reticulation system at Mayenda Village
Chikoma · water
K700,000 · Funded
Rehabilitation of market shelter at Dzalo Market (Boma)
Dzalo · markets
K650,000 · In progress
Funding year not published — 12 projects
Additional funds for construction of incinerator at Undi
Chiriwe · health
K54,000 · Approved
Battery and inverter for M'membe ECE
education
K20,000 · Approved
Construction of girls' ablution block at Kakaro Secondary School
sanitation
K700,000 · Approved
Drilling and equipping of reticulation system at Dzalo ablution block at the harbour
Dzalo · water
K270,000 · Approved
Grading of selected township roads (3 km)
roads
K300,000 · Approved
Purchase of 370 lab stools for Feira Secondary School labs
education
K425,000 · Approved
Purchase of 80 single mattresses (4 inch) for Kakaro dormitories at Kakaro Secondary School
education
K88,000 · Approved
Purchase of batteries at Yapite
equipment
K32,000 · Approved
Purchase of two water tanks at Manyenda
water
K45,000 · Approved
Rehabilitation works at Boma Police Station
security
K90,000 · Approved
Rehabilitation works at Kaunga B Health Post
Kaunga · health
K95,000 · Approved
Solar water pump kit for Feira events (opposite DC's office)
equipment
K25,000 · Approved
The audited record
The Auditor-General counted this constituency's projects in its audit of the CDF. These are the audit's own totals — a separate record from the council's published list above. The audit does not publish the projects name by name, so its totals are never added to the council list (some projects appear in both records). Figures are as printed in the Auditor-General's reports — where a report does not publish a figure, this page says so rather than estimating it.
Financial year 2024
| Component | Total funds available | Spent | Unspent | Unspent / spent |
|---|---|---|---|---|
| Community Projects | K23,374,096 | K20,639,756 | K2,734,340 | 12% unspent · 88% spent |
| Empowerment Grant | K2,479,238 | K2,180,400 | K298,838 | 12% unspent · 88% spent |
| Secondary Boarding and Skills Development - Bursaries | K5,570,545 | K4,720,014 | K850,531 | 15% unspent · 85% spent |
| Loans | K4,773,747 | K4,756,837 | K16,910 | 0% unspent · 100% spent |
| Administrative Cost | K1,600,181 | K2,837,276 | -K1,237,095 | -77% unspent · 177% spent |
Community Projects: balance brought forward K13,789,199 · 2024 funding K9,584,897
Empowerment Grant: balance brought forward K131,000 · 2024 funding K2,348,238 · other receipts K0
Secondary Boarding and Skills Development - Bursaries: balance brought forward K0 · 2024 funding K5,570,545
Loans: balance brought forward K2,864,178 · 2024 funding K1,756,421 · loan repayments received K146,294 · interest accrued K6,854
Administrative Cost: balance brought forward K0 · 2024 funding K1,531,782 · other receipts K68,399
2023 cohort — brought forward: 2 projects
2024 cohort — approved: 42 projects
Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2024 — Appendices 2.1–2.5 (money) and Appendix 3 (project status). Read the report (PDF)
Financial year 2023
| Component | Amount received | Spent | Unspent | Unspent / spent |
|---|---|---|---|---|
| Community Projects | K15,331,978 | K15,204,836 | K127,142 | 1% unspent · 99% spent |
| Empowerment Grants | K2,151,857 | K2,111,982 | K39,875 | 2% unspent · 98% spent |
| Soft Loans | Not published by constituency in the FY2023 report — its Appendix 2.3 repeats the Empowerment Grants table instead of a loans table. | |||
| Secondary Boarding and Skills Development - Bursaries | K5,379,641 | K2,184,764 | K3,194,877 | 59% unspent · 41% spent |
| Administrative Costs | K1,300,015 | K1,415,695 | -K115,680 | -9% unspent · 109% spent |
2022 cohort — brought forward: 1 projects
2023 cohort — approved: 42 projects
Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2023 — Appendices 2.1–2.5 (money) and Appendices 3–4 (project status). Read the report (PDF)