Lusaka Province · 33 published CDF projects tracked across all published years · K2,750,629 in published budgets (2 of 33 projects publish amounts). Funding year is published for 33 of 33.
Approved: 5 · Completed: 20 · In progress: 8
Record: based on council newsletters.
2023 CDF — 15 projects
Construction of 1x3 classroom block at Lishiko Primary School (incl. 70 desks)
Lukolongo · education
Not published · Approved
Construction of Chipapa Health Post at Mwando Village
Malundu Ward · health
K350,629 · Completed
Construction of bridge between Kasenje Community (C5) and (C7)
Kasenje · infrastructure
Not published · Approved
Construction of health post in Chilambila with water supply and incinerator
Chifwema · health
Not published · Approved
Construction of health post in Chipongwe with incinerator and water supply
Shimabala · health
Not published · Approved
Electrification of 4 staff houses at Likasa Secondary School
Lukolongo · education
Not published · In progress
Pothole patching on Niger Drive
Kasenje · roads
Not published · In progress
Procurement of 14-tonne vibratory steel roller compactor
Kafue Constituency · equipment
Not published · Approved
Procurement of 2,910 desks
Kafue Constituency · education
Not published · Completed
Procurement of 20,000-litre water bowser
Kafue Constituency · equipment
Not published · Completed
Spot graveling of roads (4 km)
Shikoswe · roads
Not published · In progress
Spot graveling of roads (4 km)
Kabweza · roads
Not published · In progress
Spot graveling of roads (4 km)
Chiawa · roads
Not published · In progress
Spot graveling of roads (5 km)
Chifwema · roads
Not published · In progress
Spot graveling of roads (5 km)
Magoba · roads
Not published · In progress
2022 CDF — 18 projects
Completion of 1x3 classroom block at Chiparamba Primary School
Shabusale · education
Not published · Completed
Completion of Railway Side Community School
Matanda · education
Not published · Completed
Completion of Shantumbu Police Post
Chisankane · security
Not published · Completed
Construction of 1x3 classroom block at Chikupi Primary School
Chikupi · education
Not published · Completed
Construction of 1x3 classroom block, ablution block and solar borehole at Mulangwa Primary School
Kambale · education
Not published · In progress
Construction of Kafue Main Police Station in Kafue Town (CBD) with 5000L tank
Kafue Town · security
K2,400,000 · Completed
Construction of ablution block and water reticulation at Kanyangala Health Post
Chitende · sanitation
Not published · Completed
Drilling of solar-powered borehole at Simwando Clinic
Malundu · water
Not published · Completed
Electrification, ceiling board and minor works at Kabweza Maternity Ward
Kabweza · health
Not published · Completed
Fabrication and supply of 100 double-seater desks and 100 tables and chairs for Mungu Primary School
Mungu · education
Not published · Completed
Procurement of Land Cruiser for CDF monitoring
Kafue Constituency · equipment
Not published · Completed
Procurement of motor grader
Kafue Constituency · equipment
Not published · Completed
Procurement of tipper truck
Kafue Constituency · equipment
Not published · Completed
Rehabilitation of Kambale Market Shelter
Kambale · markets
Not published · Completed
Rehabilitation of blown-off roof at Chipapa Primary School
Malundu · education
Not published · Completed
Rehabilitation of blown-off roof for classroom block at Soloboni Primary School
Shabusale · education
Not published · Completed
Repair of TLB engine
Kafue Constituency · equipment
Not published · Completed
Upgrading of water supply to solar-powered borehole with 5000L tank at Kanyangala Health Post
Chitende · water
Not published · Completed
The audited record
The Auditor-General counted this constituency's projects in its audit of the CDF. These are the audit's own totals — a separate record from the council's published list above. The audit does not publish the projects name by name, so its totals are never added to the council list (some projects appear in both records). Figures are as printed in the Auditor-General's reports — where a report does not publish a figure, this page says so rather than estimating it.
Financial year 2024
| Component | Total funds available | Spent | Unspent | Unspent / spent |
|---|---|---|---|---|
| Community Projects | K24,770,588 | K17,682,766 | K7,087,822 | 29% unspent · 71% spent |
| Empowerment Grant | K792,924 | K2,902,338 | -K2,109,414 | -266% unspent · 366% spent |
| Secondary Boarding and Skills Development - Bursaries | K2,056,338 | K5,977,110 | -K3,920,772 | -191% unspent · 291% spent |
| Loans | K5,011,475 | K4,949,586 | K61,889 | 1% unspent · 99% spent |
| Administrative Cost | K2,060,150 | K3,091,952 | -K1,031,802 | -50% unspent · 150% spent |
Community Projects
balance brought forward K20,362,763 · 2024 funding K4,407,825
Empowerment Grant
balance brought forward K32,924 · 2024 funding K760,000
Secondary Boarding and Skills Development - Bursaries
balance brought forward K156,338 · 2024 funding K1,900,000
Loans
balance brought forward K1,263,139 · 2024 funding K2,432,175 · loan repayments received K1,067,971 · interest accrued K248,190
Administrative Cost
balance brought forward K1,560,150 · 2024 funding K500,000
Community Projects: balance brought forward K20,362,763 · 2024 funding K4,407,825
Empowerment Grant: balance brought forward K32,924 · 2024 funding K760,000
Secondary Boarding and Skills Development - Bursaries: balance brought forward K156,338 · 2024 funding K1,900,000
Loans: balance brought forward K1,263,139 · 2024 funding K2,432,175 · loan repayments received K1,067,971 · interest accrued K248,190
Administrative Cost: balance brought forward K1,560,150 · 2024 funding K500,000
2023 cohort — brought forward: 9 projects
2024 cohort — approved: 16 projects
Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2024 — Appendices 2.1–2.5 (money) and Appendix 3 (project status). Read the report (PDF)
Financial year 2023
| Component | Amount received | Spent | Unspent | Unspent / spent |
|---|---|---|---|---|
| Community Projects | K15,216,296 | K2,923,917 | K12,292,379 | 81% unspent · 19% spent |
| Empowerment Grants | K2,151,857 | K2,169,800 | -K17,943 | -1% unspent · 101% spent |
| Soft Loans | Not published by constituency in the FY2023 report — its Appendix 2.3 repeats the Empowerment Grants table instead of a loans table. | |||
| Secondary Boarding and Skills Development - Bursaries | K5,379,641 | K4,536,080 | K843,561 | 0% unspent · 100% spent |
| Administrative Costs | K1,415,695 | K1,881,613 | -K465,918 | -33% unspent · 133% spent |
Community Projects
Empowerment Grants
Soft Loans
Not published by constituency in the FY2023 report — its Appendix 2.3 repeats the Empowerment Grants table instead of a loans table.
Secondary Boarding and Skills Development - Bursaries
Administrative Costs
2022 cohort — brought forward: 11 projects
2023 cohort — approved: 17 projects
Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2023 — Appendices 2.1–2.5 (money) and Appendices 3–4 (project status). Read the report (PDF)