Kasempa constituency

18 CDF projects tracked in Kasempa, North-Western: budgets, status, contractors and sources.

North-Western Province · 18 published CDF projects tracked across all published years · K1,430,671 in published budgets (2 of 18 projects publish amounts). Funding year is published for 17 of 18.

Approved: 16 · Completed: 2

Record: based on approval lists, commissioning / handover reports.

2023 CDF — 17 projects

Construction of 1x2 CRB at Kapengele Primary School

Mukema · education

Not published · Approved

Construction of 1x3 CRB at Jifumpa Primary School

Jifumpa · education

Not published · Approved

Construction of Chief Palaces at Senior Chief Kasempa and Chief Ingwe Palaces

Kalombe/Kankoonkolo · infrastructure

Not published · Approved

Construction of Water Supply System in Muselepete Compound

Kamusongolwa · water

Not published · Approved

Construction of a 1x2 CRB at Kabote Community Primary School

Kamakuku · education

Not published · Approved

Construction of a 1x2 Science Lab/Computer Lab at Nkenyauna Day Secondary School

Nkenyauna · education

Not published · Approved

Construction of a 1x3 CRB at Kansono Community Primary School

Kamatete · education

Not published · Approved

Construction of a 1x3 CRB at Maako Primary School

Maako · education

Not published · Approved

Construction of a 1x3 CRB at Shibende Primary School

Shibende · education

K730,671 · Completed

Construction of a Maternity Annex with Solar Installation at Kelongwa Health Center

Kelongwa · health

Not published · Approved

Construction of a Staff House at Ngoma Primary School

Kamakechi · education

Not published · Approved

Drilling of 30 Boreholes

All Wards · water

Not published · Approved

Procurement of Desks Across All Schools in the District

All Wards · education

Not published · Approved

Procurement of Police Motor Vehicle

All Wards · equipment

Not published · Approved

Procurement of Tipper Truck

All Wards · equipment

Not published · Approved

Servicing of Earth Moving Equipment (Grader and Front End Loader)

All Wards · equipment

Not published · Approved

Supplying of Electricity Across the District

All Wards · infrastructure

Not published · Approved

Funding year not published — 1 projects

The audited record

The Auditor-General counted this constituency's projects in its audit of the CDF. These are the audit's own totals — a separate record from the council's published list above. The audit does not publish the projects name by name, so its totals are never added to the council list (some projects appear in both records). Figures are as printed in the Auditor-General's reports — where a report does not publish a figure, this page says so rather than estimating it.

Financial year 2024

ComponentTotal funds availableSpentUnspentUnspent / spent
Community ProjectsK17,981,176K15,122,107K2,859,06916% unspent · 84% spent
Empowerment GrantK2,263,000K2,263,000K00% unspent · 100% spent
Secondary Boarding and Skills Development - BursariesK5,603,782K5,603,782K00% unspent · 100% spent
LoansK4,270,664K3,182,400K1,088,26425% unspent · 75% spent
Administrative CostK2,298,154K2,298,154K00% unspent · 100% spent

Community Projects: balance brought forward K5,564,292 · 2024 funding K12,416,884

Empowerment Grant: balance brought forward K507,535 · 2024 funding K1,755,465

Secondary Boarding and Skills Development - Bursaries: balance brought forward K1,215,120 · 2024 funding K4,388,662

Loans: balance brought forward K396,694 · 2024 funding K3,382,299 · loan repayments received K424,907 · interest accrued K66,764

Administrative Cost: balance brought forward K1,143,253 · 2024 funding K1,154,901

2023 cohort — brought forward: 1 projects

Implemented — 1 (100%)In progress — 0 (0%)Not implemented — 0 (0%)

2024 cohort — approved: 17 projects

Implemented — 3 (18%)In progress — 13 (76%)Not implemented — 1 (6%)

Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2024 — Appendices 2.1–2.5 (money) and Appendix 3 (project status). Read the report (PDF)

Financial year 2023

ComponentAmount receivedSpentUnspentUnspent / spent
Community ProjectsK13,688,942K7,341,567K6,347,37546% unspent · 54% spent
Empowerment GrantsK1,921,255K2,890,606-K969,351-50% unspent · 150% spent
Soft LoansNot published by constituency in the FY2023 report — its Appendix 2.3 repeats the Empowerment Grants table instead of a loans table.
Secondary Boarding and Skills Development - BursariesK4,803,138K5,386,606-K583,468-12% unspent · 112% spent
Administrative CostsK1,263,984K1,953,037-K689,053-55% unspent · 155% spent

2022 cohort — brought forward: 23 projects

Implemented — 20 (87%)In progress — 0 (0%)Not implemented — 3 (13%)

2023 cohort — approved: 17 projects

Implemented — 7 (41%)In progress — 7 (41%)Not implemented — 3 (18%)

Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2023 — Appendices 2.1–2.5 (money) and Appendices 3–4 (project status). Read the report (PDF)