Eastern Province · 15 published CDF projects tracked across all published years · per-project amounts not published in published budgets (0 of 15 projects publish amounts). Funding year is published for 15 of 15.
Approved: 15
Record: based on approval lists.
Bridge Construction (Umi Zone Community) - Construction of Crossing Point (Umi Community)
Nthitimila · infrastructure
Not published · Approved
Completion of 1x3 Classroom Block at Chindindindi Community School
Nthitimila · education
Not published · Approved
Completion of 1x3 Classroom Block at Kamilenje Primary School
Chilola · education
Not published · Approved
Completion of the District Parliamentary Office and Ablution Block
Mnyamazi · administration
Not published · Approved
Construction of 1x3 Classroom Block at Chikhumbi Primary School
Lunevwa · education
Not published · Approved
Construction of 1x3 Classroom Block at Kakota Community School
Ndonda · education
Not published · Approved
Construction of 1x3 Classroom Block at Kakumba Primary School
Msuzi · education
Not published · Approved
Construction of 1x3 Classroom Block at Kazinda Primary School
Mphamba · education
Not published · Approved
Construction of 1x3 Classroom Block at Nthakalavu Primary School
Chimaliro · education
Not published · Approved
Construction of 1x6 Two Storey Classroom Block at Lundazi Day Secondary School
Mnyamazi · education
Not published · Approved
Construction of Mphandu-Pandu Health Post
Vuu · health
Not published · Approved
Construction of a Crossing Point at Chanyondo to Vakaza
Mkomba · infrastructure
Not published · Approved
Installation of Solar System and Air Conditioner (Lundazi Town Council) and Rehabilitation of the Council Chamber
Lundazi · administration
Not published · Approved
Maintenance and Repair of Procured CDF Vehicles (Skip Truck and Land Cruiser)
Lundazi · equipment
Not published · Approved
Purchase of Equipment for Health Posts in Lundazi District
Lundazi · equipment
Not published · Approved
The audited record
The Auditor-General counted this constituency's projects in its audit of the CDF. These are the audit's own totals — a separate record from the council's published list above. The audit does not publish the projects name by name, so its totals are never added to the council list (some projects appear in both records). Figures are as printed in the Auditor-General's reports — where a report does not publish a figure, this page says so rather than estimating it.
Financial year 2024
| Component | Total funds available | Spent | Unspent | Unspent / spent |
|---|---|---|---|---|
| Community Projects | K25,085,165 | K20,260,530 | K4,824,635 | 19% unspent · 81% spent |
| Empowerment Grant | K2,240,000 | K2,240,000 | K0 | 0% unspent · 100% spent |
| Secondary Boarding and Skills Development - Bursaries | K5,386,714 | K5,386,714 | K0 | 0% unspent · 100% spent |
| Loans | K4,465,393 | K3,630,000 | K835,393 | 19% unspent · 81% spent |
| Administrative Cost | K3,063,286 | K3,063,286 | K0 | 0% unspent · 100% spent |
Community Projects: balance brought forward K13,837,833 · 2024 funding K11,247,332
Empowerment Grant: balance brought forward K630,907 · 2024 funding K1,609,093
Secondary Boarding and Skills Development - Bursaries: balance brought forward K1,363,981 · 2024 funding K4,022,733
Loans: balance brought forward K254,781 · 2024 funding K3,234,505 · loan repayments received K736,729 · interest accrued K239,378
Administrative Cost: balance brought forward K2,004,672 · 2024 funding K1,058,614
2023 cohort — brought forward: 5 projects
2024 cohort — approved: 22 projects
Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2024 — Appendices 2.1–2.5 (money) and Appendix 3 (project status). Read the report (PDF)
Financial year 2023
| Component | Amount received | Spent | Unspent | Unspent / spent |
|---|---|---|---|---|
| Community Projects | K14,244,118 | K2,603,167 | K11,640,951 | 82% unspent · 18% spent |
| Empowerment Grants | K2,071,872 | K2,040,000 | K31,872 | 2% unspent · 98% spent |
| Soft Loans | Not published by constituency in the FY2023 report — its Appendix 2.3 repeats the Empowerment Grants table instead of a loans table. | |||
| Secondary Boarding and Skills Development - Bursaries | K5,179,679 | K2,210,703 | K2,968,976 | 57% unspent · 43% spent |
| Administrative Costs | K1,363,074 | K1,750,926 | -K387,852 | -28% unspent · 128% spent |
2022 cohort — brought forward: 25 projects
2023 cohort — approved: 19 projects
Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2023 — Appendices 2.1–2.5 (money) and Appendices 3–4 (project status). Read the report (PDF)