Zambia CDF Tracker

Malole constituency

CDF in Malole, Northern: K40m allocated in 2026; project-level tracking has not reached this constituency yet — the publishing gap is part of the record.

Northern Province · project-level tracking has not reached this constituency yet.

The publishing gap is part of the record

Malole receives the same CDF allocation as every constituency — K40m in 2026. What its council has not yet published, in any list we can verify, is which projects that money is funding. This page will fill in as soon as a publishable list exists; the weekly check watches for one.

See Northern Province — allocations by year and all its constituencies

The audited record

The Auditor-General counted this constituency's projects in its audit of the CDF. These are the audit's own totals — a separate record from the council's published list above. The audit does not publish the projects name by name, so its totals are never added to the council list (some projects appear in both records). Figures are as printed in the Auditor-General's reports — where a report does not publish a figure, this page says so rather than estimating it.

Financial year 2024

ComponentTotal funds availableSpentUnspentUnspent / spent
Community ProjectsK19,966,849K18,410,187K1,556,6628% unspent · 92% spent
Empowerment GrantK2,163,309K2,163,309K00% unspent · 100% spent
Secondary Boarding and Skills Development - BursariesK5,003,523K5,003,523K00% unspent · 100% spent
LoansK4,168,689K3,492,463K676,22616% unspent · 84% spent
Administrative CostK397,372K1,938,958-K1,541,586-388% unspent · 488% spent

Community Projects: balance brought forward K16,664,854 · 2024 funding K3,301,995

Empowerment Grant: balance brought forward K2,163,309 · 2024 funding K0

Secondary Boarding and Skills Development - Bursaries: balance brought forward K5,003,523 · 2024 funding K0

Loans: balance brought forward -K32,674 · 2024 funding K3,496,226 · loan repayments received K679,890 · interest accrued K25,247

Administrative Cost: balance brought forward K397,372 · 2024 funding K0

2023 cohort — brought forward: 3 projects

Implemented — 0 (0%)In progress — 3 (100%)Not implemented — 0 (0%)

2024 cohort — approved: 11 projects

Implemented — 4 (36%)In progress — 3 (27%)Not implemented — 4 (36%)

Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2024 — Appendices 2.1–2.5 (money) and Appendix 3 (project status). Read the report (PDF)

Financial year 2023

ComponentAmount receivedSpentUnspentUnspent / spent
Community ProjectsK9,962,344K785,439K9,176,90592% unspent · 8% spent
Empowerment GrantsK2,151,857K2,151,815K420% unspent · 100% spent
Soft LoansNot published by constituency in the FY2023 report — its Appendix 2.3 repeats the Empowerment Grants table instead of a loans table.
Secondary Boarding and Skills Development - BursariesK5,179,641K5,338,841-K159,200-3% unspent · 103% spent
Administrative CostsK1,415,695K1,059,048K356,64725% unspent · 75% spent

2022 cohort — brought forward: 39 projects

Implemented — 28 (72%)In progress — 6 (15%)Not implemented — 5 (13%)

2023 cohort — approved: 14 projects

Implemented — 3 (21%)In progress — 8 (57%)Not implemented — 3 (21%)

Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2023 — Appendices 2.1–2.5 (money) and Appendices 3–4 (project status). Read the report (PDF)

?How to read
this tracker