Zambia CDF Tracker

Matero constituency

13 CDF projects tracked in Matero, Lusaka: budgets, status, contractors and sources.

Lusaka Province · 13 published CDF projects tracked across all published years · K17.6m in published budgets (13 of 13 projects publish amounts). Funding year is published for 13 of 13.

Approved: 12 · Completed: 1

Record: based on approval lists.

2025 CDF — 12 projects

2023 CDF — 1 projects

The audited record

The Auditor-General counted this constituency's projects in its audit of the CDF. These are the audit's own totals — a separate record from the council's published list above. The audit does not publish the projects name by name, so its totals are never added to the council list (some projects appear in both records). Figures are as printed in the Auditor-General's reports — where a report does not publish a figure, this page says so rather than estimating it.

Financial year 2024

ComponentTotal funds availableSpentUnspentUnspent / spent
Community ProjectsK22,402,759K15,366,980K7,035,77931% unspent · 69% spent
Empowerment GrantK2,056,116K2,056,116K00% unspent · 100% spent
Secondary Boarding and Skills Development - BursariesK4,818,682K4,218,345K600,33712% unspent · 88% spent
LoansK7,044,093K6,381,814K662,2799% unspent · 91% spent
Administrative CostK1,428,178K9,301,931-K7,873,753-551% unspent · 651% spent

Community Projects

Total funds availableK22,402,759
SpentK15,366,980
UnspentK7,035,779
Unspent / spent31% unspent · 69% spent

balance brought forward K22,218,697 · 2024 funding K184,062

Empowerment Grant

Total funds availableK2,056,116
SpentK2,056,116
UnspentK0
Unspent / spent0% unspent · 100% spent

balance brought forward K2,056,116 · 2024 funding K0

Secondary Boarding and Skills Development - Bursaries

Total funds availableK4,818,682
SpentK4,218,345
UnspentK600,337
Unspent / spent12% unspent · 88% spent

balance brought forward K4,218,345 · 2024 funding K600,337

Loans

Total funds availableK7,044,093
SpentK6,381,814
UnspentK662,279
Unspent / spent9% unspent · 91% spent

balance brought forward K326,120 · 2024 funding K6,013,822 · loan repayments received K431,817 · interest accrued K272,334

Administrative Cost

Total funds availableK1,428,178
SpentK9,301,931
Unspent-K7,873,753
Unspent / spent-551% unspent · 651% spent

balance brought forward K1,428,178 · 2024 funding K0

Community Projects: balance brought forward K22,218,697 · 2024 funding K184,062

Empowerment Grant: balance brought forward K2,056,116 · 2024 funding K0

Secondary Boarding and Skills Development - Bursaries: balance brought forward K4,218,345 · 2024 funding K600,337

Loans: balance brought forward K326,120 · 2024 funding K6,013,822 · loan repayments received K431,817 · interest accrued K272,334

Administrative Cost: balance brought forward K1,428,178 · 2024 funding K0

2023 cohort — brought forward: 4 projects

Implemented — 4 (100%)In progress — 0 (0%)Not implemented — 0 (0%)

2024 cohort — approved: 12 projects

Implemented — 11 (92%)In progress — 1 (8%)Not implemented — 0 (0%)

Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2024 — Appendices 2.1–2.5 (money) and Appendix 3 (project status). Read the report (PDF)

Financial year 2023

ComponentAmount receivedSpentUnspentUnspent / spent
Community ProjectsK11,566,703K2,659,048K8,907,65577% unspent · 23% spent
Empowerment GrantsK1,955,843K1,955,843K00% unspent · 100% spent
Soft LoansNot published by constituency in the FY2023 report — its Appendix 2.3 repeats the Empowerment Grants table instead of a loans table.
Secondary Boarding and Skills Development - Bursaries†Not publishedNot publishedNot publishedNot published
Administrative CostsK1,286,739K1,258,371K28,3682% unspent · 98% spent

Community Projects

Amount receivedK11,566,703
SpentK2,659,048
UnspentK8,907,655
Unspent / spent77% unspent · 23% spent

Empowerment Grants

Amount receivedK1,955,843
SpentK1,955,843
UnspentK0
Unspent / spent0% unspent · 100% spent

Soft Loans

Not published by constituency in the FY2023 report — its Appendix 2.3 repeats the Empowerment Grants table instead of a loans table.

Secondary Boarding and Skills Development - Bursaries†

Amount receivedNot published
SpentNot published
UnspentNot published
Unspent / spentNot published

Administrative Costs

Amount receivedK1,286,739
SpentK1,258,371
UnspentK28,368
Unspent / spent2% unspent · 98% spent

† The report prints this constituency inside a district-combined figure; the split by constituency is not published.

2022 cohort — brought forward: 12 projects

Implemented — 12 (100%)In progress — 0 (0%)Not implemented — 0 (0%)

2023 cohort — approved: 14 projects

Implemented — 2 (14%)In progress — 2 (14%)Not implemented — 10 (71%)

Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2023 — Appendices 2.1–2.5 (money) and Appendices 3–4 (project status). Read the report (PDF)