Zambia CDF Tracker

Mufulira constituency

1 CDF projects tracked in Mufulira, Copperbelt: budgets, status, contractors and sources.

Copperbelt Province · 1 published CDF projects tracked across all published years · per-project amounts not published in published budgets (0 of 1 projects publish amounts).

Approved: 1

Record: based on council and news reports.

The audited record

The Auditor-General counted this constituency's projects in its audit of the CDF. These are the audit's own totals — a separate record from the council's published list above. The audit does not publish the projects name by name, so its totals are never added to the council list (some projects appear in both records). Figures are as printed in the Auditor-General's reports — where a report does not publish a figure, this page says so rather than estimating it.

Financial year 2024

ComponentTotal funds availableSpentUnspentUnspent / spent
Community ProjectsK22,826,004K18,217,592K4,608,41220% unspent · 80% spent
Empowerment GrantK4,238,972K2,220,600K2,018,37248% unspent · 52% spent
Secondary Boarding and Skills Development - BursariesK6,749,325K6,943,725-K194,400-3% unspent · 103% spent
LoansK7,057,555K6,663,137K394,4186% unspent · 94% spent
Administrative CostK1,264,704K1,492,570-K227,866-18% unspent · 118% spent

Community Projects: balance brought forward K11,912,862 · 2024 funding K10,913,142

Empowerment Grant: balance brought forward K0 · 2024 funding K4,238,972

Secondary Boarding and Skills Development - Bursaries: balance brought forward K4,629,839 · 2024 funding K2,119,486

Loans: balance brought forward K2,820,000 · 2024 funding K3,923,262 · loan repayments received K183,249 · interest accrued K131,044

Administrative Cost: balance brought forward K149,185 · 2024 funding K1,115,519

2023 cohort — brought forward: 16 projects

Implemented — 16 (100%)In progress — 0 (0%)Not implemented — 0 (0%)

2024 cohort — approved: 23 projects

Implemented — 20 (87%)In progress — 0 (0%)Not implemented — 3 (13%)

Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2024 — Appendices 2.1–2.5 (money) and Appendix 3 (project status). Read the report (PDF)

Financial year 2023

ComponentAmount receivedSpentUnspentUnspent / spent
Community ProjectsK15,216,297K6,501,057K8,715,24057% unspent · 43% spent
Empowerment GrantsK2,151,857K2,143,065K8,7920% unspent · 100% spent
Soft LoansNot published by constituency in the FY2023 report — its Appendix 2.3 repeats the Empowerment Grants table instead of a loans table.
Secondary Boarding and Skills Development - BursariesK5,379,641K4,965,178K414,4638% unspent · 92% spent
Administrative CostsK1,415,695K1,795,950-K380,255-27% unspent · 127% spent

2022 cohort — brought forward: 32 projects

Implemented — 32 (100%)In progress — 0 (0%)Not implemented — 0 (0%)

2023 cohort — approved: 45 projects

Implemented — 45 (100%)In progress — 0 (0%)Not implemented — 0 (0%)

Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2023 — Appendices 2.1–2.5 (money) and Appendices 3–4 (project status). Read the report (PDF)

?How to read
this tracker