Zambia CDF Tracker

Nalikwanda constituency

18 CDF projects tracked in Nalikwanda, Western: budgets, status, contractors and sources.

Western Province · 18 published CDF projects tracked across all published years · K16.6m in published budgets (13 of 18 projects publish amounts). Funding year is published for 1 of 18.

Approved: 13 · Completed: 4 · Ongoing: 1

Record: based on approval lists.

2024 CDF — 1 projects

Funding year not published — 17 projects

Construction of a maternity annex and a water scheme at Nasange Health Post

Siyowe · health

K1,070,000 · Approved

Construction of a maternity annex and a water scheme at Sibongo Health Post

Mutondo · health

K1,075,000 · Approved

Construction of a maternity annex at Natonga Health Post

Imalyo · health

K800,000 · Approved

Construction of a rural health post, 1 no. low cost staff house and a water scheme

Nanjeko · health

K2,400,000 · Approved

Construction of a water scheme and ambulance bay at Imalyo Clinic

Imalyo · health

K450,000 · Approved

Construction of low cost staff house flat, ablution block and water scheme at Kaamba Community School

Nalwei · education

K1,470,000 · Approved

Construction of low cost staff house flat, ablution block and water scheme at Kaluwawa Community School

Mutondo · education

K1,580,000 · Approved

Construction of low cost staff house flat, ablution block and water scheme at Lulomwe Community School

Looma · education

K1,330,000 · Approved

Construction of maternity annex at Lukweta Rural Health Centre

health

Not published · Ongoing

Construction of water reticulation system at Lukalanya Primary School

water

Not published · Completed

Construction of water scheme at Liande Rural Health Post

water

Not published · Completed

Construction of water scheme at Natonga Rural Health Post

water

Not published · Completed

Procurement of 1300 desks

All Wards · education

K2,340,000 · Approved

Procurement of an ambulance

All Wards · equipment

K3,000,000 · Approved

Procurement of health facility equipment

equipment

K752,205 · Approved

Radio programs

All Wards · administration

K48,000 · Approved

Rehabilitation of a staff house at Nanjeko Rural Health Post

Nanjeko · health

K270,000 · Approved

The audited record

The Auditor-General counted this constituency's projects in its audit of the CDF. These are the audit's own totals — a separate record from the council's published list above. The audit does not publish the projects name by name, so its totals are never added to the council list (some projects appear in both records). Figures are as printed in the Auditor-General's reports — where a report does not publish a figure, this page says so rather than estimating it.

Financial year 2024

ComponentTotal funds availableSpentUnspentUnspent / spent
Community ProjectsK18,979,527K19,213,577-K234,050-1% unspent · 101% spent
Empowerment GrantK3,188,932K3,188,932K00% unspent · 100% spent
Secondary Boarding and Skills Development - BursariesK3,599,200K3,599,200K00% unspent · 100% spent
LoansK495,369K323,909K171,46035% unspent · 65% spent
Administrative CostK1,246,544K1,912,890-K666,346-53% unspent · 153% spent

Community Projects: balance brought forward K12,008,755 · 2024 funding K6,970,772

Empowerment Grant: balance brought forward K3,188,932 · 2024 funding K0

Secondary Boarding and Skills Development - Bursaries: balance brought forward K3,599,200 · 2024 funding K0

Loans: balance brought forward K237,395 · 2024 funding K0 · loan repayments received K108,832 · interest accrued K149,142

Administrative Cost: balance brought forward K46,544 · 2024 funding K1,200,000

2023 cohort — brought forward: 32 projects

Implemented — 24 (75%)In progress — 8 (25%)Not implemented — 0 (0%)

2024 cohort — approved: 22 projects

Implemented — 8 (36%)In progress — 13 (59%)Not implemented — 1 (5%)

Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2024 — Appendices 2.1–2.5 (money) and Appendix 3 (project status). Read the report (PDF)

Financial year 2023

ComponentAmount receivedSpentUnspentUnspent / spent
Community ProjectsK15,057,112K3,438,354K11,618,75877% unspent · 23% spent
Empowerment GrantsK2,107,469K2,107,469K00% unspent · 100% spent
Soft LoansNot published by constituency in the FY2023 report — its Appendix 2.3 repeats the Empowerment Grants table instead of a loans table.
Secondary Boarding and Skills Development - BursariesK5,357,662K3,815,282K1,542,38029% unspent · 71% spent
Administrative CostsK1,386,492K1,339,948K46,5443% unspent · 97% spent

2022 cohort — brought forward: 30 projects

Implemented — 10 (33%)In progress — 20 (67%)Not implemented — 0 (0%)

2023 cohort — approved: 16 projects

Implemented — 4 (25%)In progress — 5 (31%)Not implemented — 7 (44%)

Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2023 — Appendices 2.1–2.5 (money) and Appendices 3–4 (project status). Read the report (PDF)

?How to read
this tracker