Completed Mapatizya, Southern Province
Contract basis from the council's minutes of 15 May 2024 (PWD/606/05/24): tendered at a contract sum of K952,622.60 to Hob-Tech Investments; works had reached roof level. Completion from the council's Plans, Works and Development Committee minutes of 27 March 2025 (PWD/944/03/25), CDF 2023 status update table: status printed as Completed, allocation K1,175,000.00 — "Construction works were completed and project is awaiting branding and official commissioning." The budget shown is the awarded contract sum; the table's allocation is the higher figure.